As you can see, the kids' room are ready to be primed. The baseboards, window trim, and closet doors have been installed. The wall texturing is complete.
Monday, April 29, 2013
Tuesday, April 23, 2013
Thursday, April 18, 2013
Drywall is done.
As you can see, the bedrooms are completely drywalled and mudding has begun. The only thing not finished having drywall hung is the kids' bathroom. We have to do some minor framing work in order to finish the bathroom.
This is how she looks today with both windows on the front in and the front door door installed.
Wednesday, April 3, 2013
Monday, April 1, 2013
More drywall installation
Yes, a DIY house rebuild takes forever. However, it also saves money. Lots of money. This is where we are currently on the drywall installation.
The hallway |
Kid Room |
Master Bedroom |
Master Closet |
Another Kid Room |
Master Bathroom |
The pit to the basement. This was entertaining watching the drywall be hung. |